Supplier prices barely moved this cycle: 151 lines re-read on 04/11/2026 shifted two build-ups. The changes in this issue are ours. One paint rate was doing the work of fifty, and the library was still burning May's diesel. Both are fixed, and the workbook gains civil rates. 23 of the 339 build-ups in the October library moved, all of them up, by a median 10.7%.
Rate update
Three things that changed the bill
- +10.7%
- Median move
- 23
- Rates up
- 0
- Rates down
- 316
- Unchanged
01 · Paintwork
+10.1%
Paint is now priced by specification
Until this issue one build-up, PVA at R83.90 a square metre, sat behind 78 of the 101 Paintwork items, enamel on steel and varnish on timber included. The bill now carries one priced line per specification: 342 items on 55 coat-by-coat systems. Primer and two coats of PVA is R92.41, primer and two coats of superior acrylic R98.85, steel primer and two coats of polyurethane enamel R150.65. Narrow work measured by the metre used to carry a square-metre rate of R141.97. It now runs from R24.97 to R69.67 a metre.
02 · Plant
+19.8%
Diesel was stale and machine rates were low
The library carried diesel at R21.50 a litre from the May capture. It is now R30.85, the wholesale 0.05% price inland from 04/11/2026. Machine excavation moves from R56.95 to R68.23 a cube, cart away from R66.07 to R79.22, and the hard rock extra-over from R594.68 to R699.86. Twenty-one build-ups from the October library moved on this correction alone. The levy relief on diesel ends on 01/12/2026, so the figure gets another look next issue.
03 · Civil
40 build-ups
Civil rates, first pass
Forty civil build-ups join the library for bulk earthworks, roads and paving, stormwater and sewers, on dry-hire plant rates read from PlantIndex on 11/11/2026. No supplier publishes a price for asphalt or concrete pipe supply, so those need a quotation. Plant outputs and fuel consumption are our own estimates and every line says so. Check them against your own production before you price with them.
The movers
23/10 to 11/11
UpDown
| Material | Movement | Change | Previous rate | New rate |
|---|---|---|---|---|
| Pumping (one pump running) hr | +29.6% | R 35.59 | R 46.11 | |
| Extra-over rock m² | +21.0% | R 200.55 | R 242.63 | |
| Cart away m³ | +19.9% | R 66.07 | R 79.22 | |
| Excavation (machine) m³ | +19.8% | R 56.95 | R 68.23 | |
| Extra-over for soft rock m³ | +18.1% | R 348.53 | R 411.64 | |
| Excavation 4–6m deep (machine) m³ | +17.7% | R 118.94 | R 139.97 | |
| Extra-over for hard rock m³ | +17.7% | R 594.68 | R 699.86 | |
| Excavation 2–4m deep (machine) m³ | +17.2% | R 91.48 | R 107.26 | |
| Strip topsoil / grade not exceeding 150mm m² | +16.8% | R 12.52 | R 14.62 | |
| Site clearance m² | +15.8% | R 9.98 | R 11.55 | |
| Tree/stump removal no | +14.2% | R 443.93 | R 507.04 | |
| Break out brickwork m³ | +10.7% | R 392.97 | R 435.05 | |
| Break out concrete m³ | +10.3% | R 610.82 | R 673.93 | |
| Rockery boulder placed (from stockpile) no | +8.8% | R 119.59 | R 130.11 | |
| Remove hedge m | +6.1% | R 86.82 | R 92.08 | |
| Remove wall m² | +5.8% | R 73.05 | R 77.26 | |
| Break up concrete surface bed / paving m² | +5.8% | R 90.45 | R 95.71 | |
| Break out slab m² | +5.4% | R 98.27 | R 103.53 | |
| Break out reinforced concrete m³ | +3.5% | R 902.18 | R 933.74 | |
| Saw-cut joint in concrete m | +3.3% | R 31.69 | R 32.74 | |
| Timber handrail / mopstick m | +2.0% | R 167.38 | R 170.80 | |
| Hurricane fastener no | +1.9% | R 33.28 | R 33.92 | |
| Break up reinforced concrete slab m² | +1.9% | R 283.35 | R 288.61 | |
−30%0%+30% |
Read-across
At the counter
Supplier prices behind the moves
- Galvanised hurricane clip/truss hanger (each) at Cashbuild. R7.00 to R8.95 per recipe unit (+27.9%).
- PVC handrail cover (per m) at Chamberlains. R99.67 to R103.00 per recipe unit (+3.3%).
- Cement 42.5N 50kg at Buildmate. R151.00 to R152.98 per recipe unit (+1.3%).
- Cement 42.5N 50kg at Builders. R122.00 to R123.00 per recipe unit (+0.8%).
On the watch list
- Diesel relief ends on 01/12. The fuel levy on diesel is cut by R3.00 a litre from 04/11 to 01/12/2026, with a smaller cut running to 05/01/2027. Wholesale 0.05% diesel fell R1.10 to R30.85 on 04/11. Price plant-heavy work on a dated fuel figure.
- MPC on 19/11. The repo rate is 7.25% and prime 10.75% after September's 25 basis point hike. CPI was 4.5% for September, and October's figure is due on 18/11/2026.
- CPAP for September is out. Stats SA's P0151.1 puts the construction input price index at +7.7% on the year and −0.4% on the month, and civil engineering materials at +3.5% and −1.1%. Haylett calculations can run on the September work-group indices.
- Some paint lines are sale prices. Several of the new paint prices were read at promotional prices at one merchant. Treat the Low column as a promotion and expect list prices nearer the High.
The workbook
Where the numbers live
Download
The priced rate library
v3.10, saved 14/11/2026. 209 materials on 542 supplier lines and 442 build-ups, with Paintwork priced by specification and civil build-ups for earthworks, roads and pipework. 151 supplier lines were re-read from live pages on 04/11/2026; 38 paint and civil lines were added on 11/11/2026. All rates recalculated with 0 formula errors. Enter quantities in column D of any bill; rates and amounts follow.
setout-rate-library-2026-11.xlsxXLSX · 1.3 MB · 37 sheets
Method
How the rates are built
Like-for-like means the same product on the same supplier listing on 23/10/2026 and 04/11/2026. A price is accepted only when read from the supplier page itself and when it lands within 67%–150% of the previous price after pack conversion; 29 lines fell outside that band and were held. Paint systems are built coat by coat: litres from the manufacturer's spread rate plus 10%, labour unchanged at 0.15 hours a coat for emulsions and 0.20 for enamels. Seven spread rates were not on any page read and are marked as assumed. Civil plant is a PlantIndex day rate divided by nine hours, dry, with operator and diesel priced separately; outputs and consumption are assumed. Profit is 12.5%. These are estimating benchmarks. Verify against project quotations before any tender award or adjudication recommendation.
Sources: [1] Department of Mineral and Petroleum Resources media statement, 03/11/2026: fuel adjustment effective 04/11/2026, diesel 0.05% down 109.82 c/l, general fuel levy relief to 01/12/2026 · [2] Stats SA, P0141 Consumer Price Index, September 2026 (released 21/10/2026): 4.5% annual; October release due 18/11/2026 · [3] SARB MPC statement, 23/09/2026: repo rate 7.25%, prime 10.75%; next meeting 19/11/2026 · [4] Stats SA, P0151.1 Construction Material Price Indices, September 2026 · [5] PlantIndex hire listings, read 11/11/2026: excavator, grader, roller, water truck, loader, tipper day rates · [6] Paint Expert, Mica, Chamberlains and Leroy Merlin product pages, read 11/11/2026: paint prices and spread rates
By Setout. General guidance, not project-specific advice.